Difference between PERT and CPM – Project Management

Difference between PERT and CPM – Project Management

Project
A project is an interrelated set of activities that has a definite starting and ending point and those results in a unique product. That means projects are not repetitive.

Few examples of projects are:
1. Constructing a bridge, dam, highway or building.
2. Producing an airplane, missile or large machine.
3. Introducing a new product.
4. Installing a large computer system.
5. Redesigning the layout of plant or office.
6. Construction of a ship.
7. Fabrication of a steam boiler.
8. Maintenance of major equipments/Plants.
9. Commissioning of a power plant/factory.
10. Conducting National Election.

Basic steps in project management
Managing a project, regardless of its size and complexity, requires identifying every activity to be undertaken and planning when each activity must begin and end in order to complete the overall project on time. Typically, all projects involve the following steps:
1. Describe the project.
2. Develop a network model.
3. Insert time estimates.
4. Analyze the model.
5. Develop the project plan.
6. Periodically assess the progress of the project and repeat steps 2-6 as needed.

Network: A network is the graphical representation of the project activities arranged in a logical sequence and depicting all the interrelationships among them.

project management basic terms
project management basic terms

Terminologies used in Network diagram:

1. Activity: An activity means work/job. It is a time consuming process. It is represented by an arrow in the network diagram (AOA system).
2. Event: An event is a specific instant of time marks the start and end of an activity.
3. Critical path: It is the sequence of activities which decides the total project duration.
4. Duration (d): Duration is the estimated or actual time required to complete a task or an activity.
5. Total project time: Time to complete the project. In other words, it is the duration of critical path.
6. Earliest start time (E): It is the earliest possible time at which an activity can start. It is calculated by moving from 1st to last event in the network diagram.
7. Latest start time (Li): It is the latest possible time by which an activity can start.
8. Earliest finish time (Ej): It is the last event time of the head event. It is calculated by moving backward in the network diagram.
9. Latest finish time (Lj): It is the last event time of the head event. It is calculated by moving backward in the network diagram.
10. Float/Slack: Slack is with reference to an event and Float is with reference to an activity.
11. Free float: (Latest Finish Time – Earliest Start Time) – Activity duration.

Network scheduling
The biggest advance in project scheduling since the development of the Gantt chart in 1917 was made between1956-58. During this period, two new scheduling techniques were developed. These techniques are
(i) Program evaluation and review technique (PERT)
(ii) Critical path method (CPM)

Both are based on the use of a network/graphical model to depict the work tasks being scheduled. The popularity of network based scheduling can be attributed to its many benefits, especially its ease use. Other benefits include the following.
1. It provides a visual display of needed task and their temporal ordering, which makes it easy to see how tasks should be sequenced as shown below. This assists communication and co-operation among task teams because each team can see how its work affects other team.
2. It provides a relatively accurate estimate of the time required to complete the project at the proposed resource level.
3. It identified and highlights the tasks that are critical to keep the project on schedule.
4. It provides a method for evaluating the time-cost tradeoffs resulting from reallocating resources among tasks.
5. It provides a method for monitoring the project throughout its life cycle. As the project progresses, PERT/CPM easily identifies change in which tasks are critical and how the expected completion date is affected.
6. It provides a convenient method for incorporating uncertainty regarding task times into the schedule and it helps to evaluate the effect of this uncertainty on project completion time.

Difference between PERT and CPM

PERTCPM
PERT is a probabilistic model with uncertainty in activity duration. Activity duration is calculated from t0, tp and tm.CPM is a deterministic model with well known activity duration.
It is an event oriented approach.It is an activity oriented approach.
PERT terminology uses word like network diagram, event and slack.CPM terminology employs word like arrow diagram, nodes and float
PERT terminology uses word like network diagram, event and slack.CPM terminology employs word like arrow diagram, nodes and float.
The use of dummy activity is required for representing the proper sequencing.No dummy activity required.
PERT basically does not demarcate between critical and non-critical activities.CPM marks the critical activities.
PERT is applied in projects where resources are always made available.CPM is applied to projects where minimum overall cost is the prime importance.
PERT is suitable in Defence project and R&D where activity time can’t be readily predicted.Suitable for plant maintenance, civil construction projects etc. where activity duration is known.

Sachin Thorat

Sachin is a B-TECH graduate in Mechanical Engineering from a reputed Engineering college. Currently, he is working in the sheet metal industry as a designer. Additionally, he has interested in Product Design, Animation, and Project design. He also likes to write articles related to the mechanical engineering field and tries to motivate other mechanical engineering students by his innovative project ideas, design, models and videos.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Recent Posts